Crestone Peak Resources anticipates beginning oil and gas development at the Kugel 18H-H267 14-horizontal well pad located in the Town of Firestone in the coming weeks. This well pad is located south of Sable Avenue, and west of Frontier Street. Crestone has provided a summary of what can be expected during operations. View the complete activity notice here.
- Pad Construction: Preparing the location (approximately eight weeks).
- Phase One - to begin in April: Drilling the 14 Kugel wells (approximately 10 days per well, 24/7 operations).
- Phase Two: Completing the wells (approximately seven days per well, 24/7 operations).
- Phase Three: Production & Reclamation (averages 20-30 days for production; reclamation times vary greatly).